How long does it take to install Pallet Racking?

If you’re planning a warehouse setup or expansion, knowing how long pallet racking installation will take is just as important as knowing what type of racking you need. The truth is, installation timelines vary significantly depending on your system’s complexity, warehouse readiness, and local code requirements. On average, a standard selective pallet racking system can take anywhere from 1 day- 2 months to install but several key decide that timeline.
⚙️ One Phase vs. Two Phases: Timing Your Project Correctly
A single-phase installation (everything installed at once) is usually the fastest route. If your warehouse is already built out and your racking plan is finalized, installation crews can get started as soon as permits are cleared and materials arrive.
However, many warehouses especially those still under construction or undergoing redesign require a two-phase installation. The first phase might include installing base-level uprights and beams to accommodate early operations, with a second phase scheduled for safety features, or layout expansions. Two-phase jobs add logistical coordination, which often adds a few extra days or even weeks, especially if materials or site conditions delay the second phase.
🧱 Add-Ons That Add Time: Wire Decks, Supports & Safety Gear
If your racking system includes wire decking, pallet supports, or safety products like column protectors and rail guards, expect those elements to increase install time. While they enhance safety and storage flexibility, they also require additional hardware and mounting time.
For example:
- Wire decks need to be placed after beam installation.
- Pallet supports must be measured and installed to match beam spacing.
- Rail guards and column protectors often require drilling into the slab or anchoring adding hours or even a day depending on the quantity.
Even though these components are often added toward the end of the install, they are critical and shouldn’t be rushed.
📏 Height Matters: The Bigger the Rack, the Longer the Build
Installing standard upright heights (12–16 feet) is typically straightforward. But once you get into taller upright systems (20–24 feet and above), things change.
Larger systems often require:
- Scissor lifts or specialized forklifts to reach top beam levels.
- Additional bracing and anchoring to meet seismic or local safety code requirements.
Plus, tall racking structures may trigger extra inspection steps from your city or county building department, which can delay project sign-off.
🧾 Other Timeline Variables: Permits, Floor Prep & Crew Size
Before installation can begin, permits and stamped drawings may be required, especially if your city mandates compliance for high-pile storage. Approval processes alone can add 2–6 weeks to your timeline.
The condition of your warehouse floor also plays a role uneven slabs may require shimming or pre-work. And of course, the size of the installation crew affects speed: a four-person team moves a lot faster than a two-person crew.
✅ Final Takeaway
So, how long does pallet racking installation take? The short answer: anywhere from 1 to 7 days for most standard warehouse setups under 50,000 SQ FT but in bigger warehouses with complex systems, phased installs, tall racks, and safety features can stretch that timeline. Planning ahead, knowing your phases, and working with experienced installers will keep your project on schedule.